| % Complete | Target Due Date |
|---|
| 0% | 12/29/2028 |
Expand to see more
Project did not begin this past quarter. Set to release the RFP in the coming months for the Bicycle and Pedestrian Master Plan update.
Click here for more information on this CIP project's budget.
| 5% | 10/31/2027 |
Expand to see more
CIty has been selected for HSIP funding and is currently developing the Project Plans, Specifications, and Estimate. Construction is expected in 2027.
Click here for more information on this CIP project's budget.
| 10% | 12/31/2027 |
Expand to see more
Request For Proposal (RFP) has been issued for design. RFP to be released to select civil engineering consultant February 2026.
Click here for more information on this CIP project's budget.
| 0% | 12/31/2027 |
Expand to see more
The program supplement agreement is being executed and signed. The project will start after the agreement execution in January 2026.
Click here for more information on this CIP project's budget.
| 40% | 04/30/2027 |
Expand to see more
Community Engagement - Conducted outreach to general public and school communities to design the Hayward Rides (Bike Giveaway) Program
Hayward Rides (Bike Giveaway) - distributed 100+ free bikes to HS students in Hayward
Active Transportation Education & Promotion - Working with TransForm, project partner, to conduct school events to encourage walking/biking
Click here for more information on this CIP project's budget.
| 80% | 09/25/2025 |
Expand to see more
Funds mostly expended. Staff is currently looking for opportunities to expend remaining funds.
Click here for more information on this CIP project's budget.
| 3% | 10/31/2027 |
Expand to see more
The project is currently in the planning phase. Design activities are scheduled to begin in Spring 2026.
Click here for more information on this CIP project's budget.
| 85% | 06/30/2026 |
Expand to see more
The Patrick Avenue component of the project is complete. Gading Road was repaved and a road diet and new bike lanes were implemented. However, there are some traffic calming measures still to be installed in Spring 2026.
Click here for more information on this CIP project's budget.
| 0% | 06/30/2025 |
Expand to see more
Click here for more information on this CIP project's budget.
| 60% | 06/30/2027 |
Expand to see more
In FY26, the project will install a total of 100 simme seats at bus stops in the City. As of 12/23/25 the first half (50) simme seats are currently being installed.
Click here for more information on this CIP project's budget.