Livable Neighborhoods > Sidewalk & Wheelchair Ramps
Projects
| % Complete | Target Due Date |
|---|
| 95% | 01/30/2026 |
Expand to see more
All bid line items completed. Final punchlist items and possible change order pending.
Click here for more information on this CIP project's budget.
| 95% | 01/30/2026 |
Expand to see more
All bid items are completed. Finishing up punchlist and possible change order pending.
Click here for more information on this CIP project's budget.
| 0% | 09/25/2025 |
Expand to see more
Started reviewing potential sites for this project.
Click here for more information on this CIP project's budget.
| 0% | 09/25/2025 |
Expand to see more
Starting on figuring out sites for this next project
Click here for more information on this CIP project's budget.
| 10% | 09/25/2025 |
Expand to see more
Portion of District 7 repair is complete.
Click here for more information on this CIP project's budget.
| 100% | 09/25/2025 |
Expand to see more
Project completed.
Click here for more information on this CIP project's budget.
| 0% | 09/25/2025 |
Expand to see more
Project to start August 2026.
Click here for more information on this CIP project's budget.