Water System Projects
Projects
| % Complete | Target Due Date |
|---|
| 10% | 09/25/2025 |
Expand to see more
CEQA completed; project goes to City Council for approval to bid on 2/3/26
Click here for more information on this CIP project's budget.
| 80% | 03/31/2026 |
Expand to see more
Project is on track. Space needs assessment has been completed. City is reviewing conceptual design options.
Click here for more information on this CIP project's budget.
| 0% | 09/25/2025 |
Expand to see more
Project not yet started.
Click here for more information on this CIP project's budget.
| 0% | 09/25/2025 |
Expand to see more
Project not yet started.
Click here for more information on this CIP project's budget.
| 0% | 09/25/2025 |
Expand to see more
Project not yet started.
Click here for more information on this CIP project's budget.
| 0% | 09/25/2025 |
Expand to see more
Project not yet started.
Click here for more information on this CIP project's budget.
| 0% | 09/15/2027 |
Expand to see more
Project not yet started.
Click here for more information on this CIP project's budget.
| 0% | 09/30/2027 |
Expand to see more
Project not yet started.
Click here for more information on this CIP project's budget.
| 60% | 08/31/2026 |
Expand to see more
The major update to the sewer and water mapbooks were completed in July 2025, and it will be an on-going effort to update as needed. The next project is implementing new features to the online GIS sewer and water maps. We received the draft of the Feasibility study, which outlines how the features can be added and the estimated cost and schedule. The final report will be completed in January 2026, and the pilot study for the features will start in February 2026.
Click here for more information on this CIP project's budget.
| 0% | 05/12/2027 |
Expand to see more
The scope of this project will be defined following the completion of the Recycled Water System Master Plan.
Click here for more information on this CIP project's budget.
| 100% | 09/25/2025 |
Expand to see more
The Risk and Resilience Assessment (RRA) and Emergency Response Plan (ERP) were certified in March 2025 and September 2025, respectively. There are no further mitigation measure recommendations; Water Resources Staff confirmed this with Water O&M.
Click here for more information on this CIP project's budget.
| 100% | 09/25/2025 |
Expand to see more
Public Water Systems (PWS) serving more than 3,000 connections are required to conduct a Risk and Resilience Assessment (RRA) and update an Emergency Response Plan (ERP) every five years as mandated by the Safe Drinking Water Act. The RRA was certified with EPA on 3/28/2025 and ERP was certified on 9/30/2025.
Click here for more information on this CIP project's budget.