Livable Neighborhoods > Parks & Landscaping
Projects
| % Complete | Target Due Date |
|---|
| 0% | June 2027 |
Expand to see more
Due to the rainy season, start-of-construction has been postponed to April 2026. Construction is expected to complete by end of June 2027.
This project is funded by Fund 405 - Capital Projects (Governmental) and currently has a Measure C contribution of $5,200,000.
Click here for more information on this CIP project's budget.
| 10% | TBD |
Expand to see more
As of early FY26, this project was put on pause due to the City's current fiscal situation.
This project is currently funded by Fund 406 - Measure C Capital in the amount of $1,200,000.
Click here for more information on this CIP project's budget.
| 100% | Complete |
Expand to see more
Substantial completion on 12/31/25. Final completion was in January 2026.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 100% | Complete |
Expand to see more
Complete
This project has a budget of $200,000 and is by funded by Fund 405 - Capital Projects (Governmental), which includes transfers from the General Fund.
Click here for more information on this CIP project's budget.
| 0% | TBD |
Expand to see more
Project is on hold pending Caltrans planning/operations in the same project footprint, as of January 20, 2026. Staff does not have a projected target start date, nor a target completion date.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.