Road & Street Projects
Projects
| % Complete | Target Due Date |
|---|
| 100% | Completed |
Expand to see more
The construction contract was completed on November 13, 2025 and was accepted as complete on January 7, 2026.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 100% | Complete |
Expand to see more
Project complete.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 5% | June 2027 |
Expand to see more
Delayed due to Federal Aviation Administration (FAA) review and consideration of streetlight location and height.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 20% | December 2028 |
Expand to see more
Working on 35% design plans and resolving comments from Diagnostic Team.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.