Livable Neighborhoods > Parks & Landscaping
Projects
| % Complete | Target Due Date |
|---|
| 30% | Q3 2027 |
Expand to see more
The project is on track. Construction work started at the end of March with grading and underground utilities installation.
This project is funded by Fund 405 - Capital Projects (Governmental); however, the originally budgeted Measure C contribution of $5,200,000 has recently been removed from this project.
Click here for more information on this CIP project's budget.
| 10% | June 2030 |
Expand to see more
Due to the City's current financial situation, the project scope was reduced by roughly 20% and put on hold in FY26 and FY27. This project is expected to recommence in FY28 and end in FY30.
This project is currently funded by Fund 406 - Measure C Capital in the amount of $1,000,000.
Click here for more information on this CIP project's budget.
| 100% | Complete |
Expand to see more
Substantial completion on December 31, 2025. Final completion on January 30, 2026. Acceptance of Work on March 24, 2026.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 0% | TBD |
Expand to see more
Project is indefinitely on hold. Caltrans is conducting capital improvements in this location which incorporate COH's intended improvements.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.