Livable Neighborhoods > Traffic Calming
Projects
| % Complete | Target Due Date |
|---|
| 0% | January 2027 |
Expand to see more
Construction has not yet started. Estimated 100% Set September 2026. Estimated Bid Advertisement to follow.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 0% | June 2028 |
Expand to see more
Project not yet started.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 5% | March 2028 |
Expand to see more
The Nighttime Safety Enhancement Plan will assess and recommend streetlight conditions and illuminance level to improve the nighttime travel safety and reduce any collisions happen in the dark conditions. The project just have began and the City is working with the consultant to collect and assess the existing streetlight conditions and preparing a listening session with Public Works staff to discuss streetlight maintenance, installations, and operations.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 95% | September 30, 2026 |
Expand to see more
Project progressed from 65% to approximately 95% PS&E (project specifications and estimate). Outstanding items C-3, Right of Way, and public outreach have been successfully completed. Staff anticipates 100% set ready by September 30, 2026 with advertisement and construction of the project to follow.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 95% | September 30, 2026 |
Expand to see more
Project progressed from 65% to approximately 95% PS&E (project specifications and estimate). Outstanding items C-3, Right of Way, and public outreach have been successfully completed. Staff anticipates 100% set ready by September 30, 2026 with advertisement and construction of the project to follow.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 60% | June 30, 2027 |
Expand to see more
Request for Proposal (RFP) for PS&E was published and awarded to Bennett Engineering. Project design has kicked off and is expected to be completed towards the end of 2026
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 65% | March 2027 |
Expand to see more
Completed 2nd round of outreach and presented alternatives to Council on June 2nd.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 100% | August 2025 |
Expand to see more
Planning and design only. Design completed August 2025.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 10% | September 2027 |
Expand to see more
Phase 1 improvements completed September/October 2025. Phase 2 (pedestrian improvements) are under design. The City is currently developing topographic survey, which is the first step in developing project Plans, Specifications, and Estimates.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 50% | November 2027 |
Expand to see more
Completed round 2 outreach and selected preferred alternatives for A Street, B Street, Tennyson Road (Phase 1). Kicked off and collected data and information for Hesperian Boulevard, Mission Boulevard, and Jackson Street (Phase 2).
Originally, this project was partially funded by Fund 460 - Transportation System Corridor which does include transfers from the General Fund and Measure C. In order to minimize the impact on General Fund, staff received City Council approval to remove the entire General Fund contribution of $264,000 for the required matching portion of the project and replace with an appropriation from Fund 213, Measure BB (Pedestrian& Bicycle).
Click here for more information on this CIP project's budget.
| 25% | July 2028 |
Expand to see more
Quick build project has been completed. Planning for permanent improvements not started.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 40% | March 2027 |
Expand to see more
Santa Clara St Safety Improvements Plan was prepared to increase travel safety and slow overall speed. The improvements plan has been presented through the survey and feedback has been collected from the residents and stakeholders. The Plan has been finalized and ready for for construction in August-September 2026.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 100% | Complete |
Expand to see more
Completed. Plan approved by City Council.
Originally, this project was partially funded by Fund 460 - Transportation System Corridor which does include transfers from the General Fund and Measure C. In order to minimize the impact on General Fund, staff received City Council approval to remove the entire General Fund contribution of $264,000 for the required matching portion of the project and replace with an appropriation from Fund 213, Measure BB (Pedestrian& Bicycle).
Click here for more information on this CIP project's budget.
| 90% | December 2027 |
Expand to see more
Infrastructure and signal timing portion of project completed. Currently in monitoring phase.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 90% | Ongoing |
Expand to see more
Ongoing implementation of the Neighborhood Traffic Calming Program and responding to resident requests.
This project is funded by Fund 460 - Transportation Improvement Fund in the amount of $150,000 for FY26. Fund 460 includes transfers from the General Fund and Measure C.
Click here for more information on this CIP project's budget.