Projects in this category involve improvements to existing municipal buildings and construction of new municipal buildings.

Projects

% Complete Target Due Date
Status Indicators: Complete On Track Ongoing Not Started Pending Delivery On Hold Delayed Abandoned
Finish a preliminary feasibility report on a new Police Building
100%

Complete

Expand to see more
Project Number: 07423

Activities:

Programming, space needs, conceptual design and site assessment for the new Public Safety Center are completed. This included a final study report which was presented to the CIAC on 2/25/26.

General Fund/Measure C Impact:

This project is funded by Fund 406 - Measure C Capital, in the amount of $625,000.

Click here for more information on this CIP project's budget.

New Fire Station No. 6
99%

November 30, 2026

Expand to see more
Project Number: 07481

Activities:

While buildings have been occupied, contractor still has remaining items in order to close out the project.

General Fund/Measure C Impact:

This project is funded by Fund 406 - Measure C Capital in the amount of $18,971,000.

Click here for more information on this CIP project's budget.

New Fire Training Center
99%

November 30, 2026

Expand to see more
Project Number: 07482

Activities:

While buildings have been occupied, contractor still has remaining items in order to close out the project.

General Fund/Measure C Impact:

This project is partially funded by Fund 406 - Measure C Capital in the amount of $41,866,000.

Click here for more information on this CIP project's budget.