Projects
| % Complete | Target Due Date |
|---|
| 100% | Complete |
Expand to see more
Programming, space needs, conceptual design and site assessment for the new Public Safety Center are completed. This included a final study report which was presented to the CIAC on 2/25/26.
This project is funded by Fund 406 - Measure C Capital, in the amount of $625,000.
Click here for more information on this CIP project's budget.
| 99% | November 30, 2026 |
Expand to see more
While buildings have been occupied, contractor still has remaining items in order to close out the project.
This project is funded by Fund 406 - Measure C Capital in the amount of $18,971,000.
Click here for more information on this CIP project's budget.
| 99% | November 30, 2026 |
Expand to see more
While buildings have been occupied, contractor still has remaining items in order to close out the project.
This project is partially funded by Fund 406 - Measure C Capital in the amount of $41,866,000.
Click here for more information on this CIP project's budget.