Sewer System Projects
Projects
| % Complete | Target Due Date |
|---|
| 30% | Late 2031 |
Expand to see more
Design for the Administration Building and Laboratory was completed in 2024, with construction beginning in May of 2025. Construction is expected to be complete in September of 2027. 100% design of the Phase II upgrade was completed in August of 2025, and work is underway to finalize the bid documents. However, bidding this project is contingent upon receiving a loan from United States Environmental Protection Agency (USEPA) Water Infrastructure Financing and Innovation Act (WIFIA) program. Finalizing this loan agreement has been paused, pending action from the USEPA. Timing of the final bid documents and beginning of construction are contingent upon finalizing the WIFIA loan agreement. In December of 2025, the City also applied for a loan through the California State Revolving Fund (SRF) program. The City anticipates receiving determination on whether we will receive SRF funding in May of 2026. The remainder of the project is primarily financed by bonds. A first round of bonds worth $125 million was issued in 2025, and second bond issue will be issued in subsequent years if necessary. Completion date is dependent upon timing of securing WIFIA loan, as well as whether SRF loan is acquired. If SRF loan is secured, some revisions to the bid package may be required which may push bidding to the end of 2026. Assuming bidding takes place in October of 2026, completion date would be late 2031.
This project has no General Fund or Measure C impact.
| 100% | Complete |
Expand to see more
Project completed.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 9% | November 1, 2027 |
Expand to see more
City Council Approval of Bid Documents scheduled for April.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 0% | TBD |
Expand to see more
Project has not started.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 100% | Complete |
Expand to see more
Construction completed as of December 2025.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 1% | December 2026 |
Expand to see more
Staff is currently gathering data and discussing the project with potential consultant.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 8% | February 2027 |
Expand to see more
Twenty-four (24) flow meters were installed. Flow monitoring has started as of December 18, 2025. We are working on gathering data from City staff (Utilities Admin, O&M, Planning, WPSC, etc.) to update the hydraulic model.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 48% | October 2026 |
Expand to see more
Consultant has been onboarded. Phase 1 ~80% complete. ~50% through the schedule
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 100% | Completed |
Expand to see more
Construction completed 9/25/25.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 70% | May 11, 2026 |
Expand to see more
Staff is developing a Recycled Water System Master Plan with estimated completion in Spring 2026, to evaluate potential water quality needs and expansion of the system to deliver recycled water to additional commercial and industrial customers.
This project has no General Fund or Measure C impact.
| 100% | Complete |
Expand to see more
Project completed.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 65% | August 2026 |
Expand to see more
Completed installation and energization of the B-side of the new Main Switchboard (MSB) in the Primary Substation Building. Installed MCC-5 and completed programming of its B-side. Performed demolition of the existing MCC-19.
This project has no General Fund or Measure C Impact.
Click here for more information on this CIP project's budget.
| 25% | August 2027 |
Expand to see more
Relocated required utilities beneath the foundation. Completed demolition of the existing parking lot. Finished over-excavation, backfilling, and trenching for foundations, including installation of underground utilities. Completed footings and grade beams. Obtained trailer permit approval for the Construction Management team and City Engineers.
This project has no General Fund or Measure C Impact.
Click here for more information on this CIP project's budget.