Projects in this category involve beautification, safety, neighborhood amenities, and improvements related to sidewalk and wheelchair infrastructure.

Projects

% Complete Target Due Date
Status Indicators: Complete On Track Ongoing Not Started Pending Delivery On Hold Delayed Abandoned
Community Based Transportation Plan
50%

December 31, 2026

Expand to see more
Project Number: 06940

Activities:

The second steering committee meeting with community stakeholders was conducted to review outreach conducted thus far and to prepare for the final outreach push for late summer. The background and existing conditions chapters of the plan have been drafted and development is on track for a final draft in December 2026.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Downtown Specific Plan Implementation (Foothill Blvd., A St., B St., and C St.)
90%

June 30, 2026

Expand to see more
Project Number: 05237

Activities:

Mission Blvd on-street parking pilot program has been installed, helping the City to study the feasibility of a road diet on Mission Blvd. City staff have performed post-project data analysis and outreach and considers the pilot project to be successful. Modifications to the pilot project to address minor issues may still occur in the next six months. The Downtown Specific Plan Implementation project also supports traffic modeling and analysis work for the downtown area.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Safe Routes for Seniors - Tennyson
30%

December 2026

Expand to see more
Project Number: 05323

Activities:

City has received final construction documents and will be heard at City Council in early Fall 2026. Construction expected Fall 2026

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Safe Routes to School Implementation Project
25%

June 30, 2027

Expand to see more
Project Number: 06941

Activities:

City has received and reviewed 90% Project Plans, Specifications, and Estimates, and is currently awaiting 100% submittal. Construction will occur in 2026 and 2027.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

City of Hayward, California | 777 B Street | Hayward, CA 94541 | 510-583-4000
City of Hayward, California | 777 B Street | Hayward, CA 94541 | 510-583-4000