| % Complete | Target Due Date |
|---|
| 100% | Complete |
Expand to see more
Project completed.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 95% | February 2026 |
Expand to see more
Due to expected delays from AT&T and PG&E, as well as extended material lead time, project completion is expected to be by end of February 2026.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 5% | July 2026 |
Expand to see more
Working on plans, specifications and estimates.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 20% | December 2028 |
Expand to see more
Received CEQA/NEPA Determination from Caltrans with cultural and biology commitments established. Working on resolving 35% design issues and coordinating with City's other project that is along Tennyson Road.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.