Road & Street Projects
Projects
| % Complete | Target Due Date |
|---|
Status Indicators:
Complete
On Track
Ongoing
Not Started
Pending Delivery
On Hold
Delayed
Abandoned
Route 238 Corridor Improvement Project - Phase 3 Final Design and Construction
| 100% | 06/30/2025 |
Expand to see more
Project Number: 05287
Activities:
Project completed.
Click here for more information on this CIP project's budget.
Main Street Complete Street Project
| 95% | 02/27/2026 |
Expand to see more
Project Number: 05283
Activities:
Due to expected delays from AT&T and PG&E, as well as extended material lead time, project completion is expected to be by end of February 2026.
Click here for more information on this CIP project's budget.
Hesperian Median Streetlight Improvement Project
| 5% | 03/31/2026 |
Expand to see more
Project Number: 05349
Activities:
Working on plans, specifications and estimates.
Click here for more information on this CIP project's budget.
Tennyson Road Crossing Safety Improvements
| 20% | 12/31/2028 |
Expand to see more
Project Number: 06944
Activities:
Received CEQA/NEPA Determination from Caltrans with cultural and biology commitments established. Working on resolving 35% design issues and coordinating with City's other project that is along Tennyson Road.
Click here for more information on this CIP project's budget.