Fleet Management
Projects
| % Complete | Target Due Date |
|---|
Status Indicators:
Complete
On Track
Ongoing
Not Started
Pending Delivery
On Hold
Delayed
Abandoned
Citywide EV Charging Upgrades
| 10% | 09/25/2025 |
Expand to see more
Project Number: 06923
Activities:
Eight EV Capable charging spaces are planned - four at the Corp Yard and four at Fire Station 1 as part of the solar and battery projects that are planned to be installed by April 2026. Additional EV charging spaces and EV vehicle purchases are on hold pending funding.
Click here for more information on this CIP project's budget.
Fire Fleet Replacement - Grants
| 100% | 09/25/2025 |
Expand to see more
Project Number: 07304
Activities:
Complete
Click here for more information on this CIP project's budget.