City of Hayward Logo
Sewer System Projects Icon

Sewer System Projects

Projects in this category support the improvement, expansion, and replacement of elements of the City of Hayward’s municipal sewer system infrastructure.

Projects

% Complete Target Due Date
Status Indicators: Complete On Track Ongoing Not Started Pending Delivery On Hold Delayed Abandoned
Design and Construct Water Pollution Control Facility Phase II upgrade
20%

2032

Expand to see more
Project Number: 07760

Activities:

Administration building and laboratory is under construction, with anticipated completion in 2027. Phase 2 Improvements design is complete but bidding and construction are on hold pending execution of federal WIFIA loan.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here to learn more about this CIP project's budget.

Annual Sewer Line Replacements FY24
10%

October 2027

Expand to see more
Project Number: 07789

Activities:

Project bidding completed and is currently in the award phase

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Annual Sewer Line Replacements FY25
0%

TBD

Expand to see more
Project Number: 07799

Activities:

Not yet started. Engineering staff is working with Utilities Operations and Maintenance staff to review maintenance data and identify utilities to be included in the project. Design is anticipated to start in winter 2026.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Annual Sewer Line Replacements FY26
0%

TBD

Expand to see more
Project Number: 07820

Activities:

Not yet started. Engineering staff is working with Utilities Operations and Maintenance staff to review maintenance data and identify utilities to be included in the project. Design is anticipated to start in winter 2026.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Sewer Trunkline Condition Assessment & Repair Scope
20%

TBD

Expand to see more
Project Number: 07823

Activities:

Inspection completed for 39-inch Valley View line

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Sewer Collection System Master Plan
55%

February 2027

Expand to see more
Project Number: 07819

Activities:

Completed flow monitoring. 24 flow meters were installed at various locations throughout the City for 2 months. Reviewed and processed water/sewer billing data to help calibrate the sewer model. Selected design and capacity criteria.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Nature-Based Solution Feasibility Study
80%

Fall 2026

Expand to see more
Project Number: 07809

Activities:

The project is approximately 80% through the schedule. Preliminary studies are complete, and 30% design documents are currently in progress. The project team has also participated in two community engagement events.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Develop a Recycled Water Master Plan
90%

August 31, 2026

Expand to see more
Project Number: 07709

Activities:

A draft version of the Recycled Water System Plan document is currently in progress. The final document will include potential projects the City can elect to implement to increase recycled water use involving the expansion of the existing recycled water treatment facilities, and the storage and distribution infrastructure. 

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here to learn more about this CIP project's budget.

WPCF (WRRF) Main 480V MCC Electrical Distribution Rehabilitation
90%

October 2026

Expand to see more
Project Number: 07656

Activities:

All electrical installation items in the Main Switchboard (MSB) building have been completed, with only punch list items remaining open. Painting, flooring, other finishes, electrical cable routing, and programming are currently in progress at the Site Waste Pump Station.

General Fund/Measure C Impact:

This project has no General Fund or Measure C Impact. 

Click here for more information on this CIP project's budget.

WPCF (WRRF) New Administration Building & Lab Project
40%

October 2027

Expand to see more
Project Number: 07786

Activities:

Ongoing activities include exterior and interior framing, gypsum board installation, MEPF (mechanical, electrical, plumbing, and fire service) installations, and underground electrical works.

General Fund/Measure C Impact:

This project has no General Fund or Measure C Impact. 

Click here for more information on this CIP project's budget.

City of Hayward, California | 777 B Street | Hayward, CA 94541 | 510-583-4000
City of Hayward, California | 777 B Street | Hayward, CA 94541 | 510-583-4000