Miscellaneous
Projects
| % Complete | Target Due Date |
|---|
| 90% | December 31, 2026 |
Expand to see more
Due to time elapsed since April 2018 adoption, the Hayward Downtown and BART Station Area Parking Management Plan will accommodate stakeholder outreach and minor adjustments prior to implementation of the proposed plan. Work this past quarter has included review and summaries of intended implementation, and outreach is set to begin in the coming months with downtown stakeholders.
This project is funded by Fund 405 - Capital Projects (Governmental), in the amount of $188,000, which does include transfers from the General Fund and Measure C.
Click here for more information on this CIP project's budget.
| 0% | 12/31/27 |
Expand to see more
Project did not begin this past quarter. Due to time elapsed since April 2018 adoption, the Hayward Downtown and BART Station Area Parking Management Plan will accommodate stakeholder outreach and minor adjustments prior to implementation of the proposed plan. Work is anticipated to begin end of FY26.
This project is funded by Fund 405 - Capital Projects (Governmental), in the amount of $100,000, which does include transfers from the General Fund and Measure C.
Click here for more information on this CIP project's budget.
| 0% | TBD |
Expand to see more
Staff are conducting discussions with developers for the BunkerHill neighborhood parcels (Rt 238 Parcel Group 5), with ongoing maintenance planning to ensure compliance with the Disposition and Development Agreement. This project supports neighborhood revitalization and economic growth.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 0% | TBD |
Expand to see more
Staff are conducting discussions with developers for the Quarry site – Overlook Ave (Rt 238 Parcel Group 6), with maintenance planning underway to ensure compliance with the Disposition and Development Agreement. This project supports redevelopment of the Quarry site, aligning with city growth and economic development goals.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 0% | TBD |
Expand to see more
Staff are conducting discussions with developers for the Foothill and Grove Way parcels (Rt 238 Parcel Group 8), with ongoing maintenance planning to ensure compliance with the Disposition and Development Agreement. This project supports local economic growth and infrastructure improvements.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 0% | TBD |
Expand to see more
Staff are conducting discussions with developers for the Apple and Oak parcels (Rt 238 Parcel Group 9), with ongoing maintenance planning to ensure compliance with the Disposition and Development Agreement. This project supports strategic development of a key site, enhancing economic growth and infrastructure near major transportation routes.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 100% | Complete |
Expand to see more
Contractor has completed work and has been paid. Project can be closed out
This project has a budget of $125,000 and is by funded by Fund 405 - Capital Projects (Governmental), which includes transfers from the General Fund.
Click here for more information on this CIP project's budget.