Construct La Vista Park
| 0% | 06/30/2027 |
Expand to see more
Project Number: 06914
Activities:
Due to the rainy season, start-of-construction has been postponed to April 2026. Construction is expected to complete by end of June 2027.
Click here for more information on this CIP project's budget.
Stack Center Construction
| 33% | 05/28/2027 |
Expand to see more
Project Number: 06960
Activities:
Phase 1 complete. Phase 2 design is complete and shovel ready. On hold until funding is secured.