Livable Neighborhoods > Traffic Calming
Projects
| % Complete | Target Due Date |
|---|
| 0% | 09/25/2025 |
Expand to see more
Project not yet started.
Click here for more information on this CIP project's budget.
| 5% | 06/30/2028 |
Expand to see more
The grant agreement was executed, and the project officially begun in FY26 (11/17/2025).
Click here for more information on this CIP project's budget.
| 65% | 12/31/2025 |
Expand to see more
Project is at 65% Level as of January 2026. Milestones are: C3, RoW Impacts, 95% Level PS&E.
Click here for more information on this CIP project's budget.
| 65% | 09/25/2025 |
Expand to see more
Project is at 65% Level as of January 2026. Milestones are: C3, Right of Way Impacts, 95% Level PS&E.
Click here for more information on this CIP project's budget.
| 55% | 12/31/2026 |
Expand to see more
Community Engagement - Conducted two outreach events to general public and families of Faith Ringgold Elementary School for input on concept design.
Applied for and received grant from Alameda County Transportation Commission for additional funding for design and construction.
RFP for PS&E is in review.
Click here for more information on this CIP project's budget.
| 40% | 03/01/2027 |
Expand to see more
Completed first round of outreach and presented recommended Downtown alternatives in an October CIAC meeting to move forward with further analyses and outreach. Started development of round two outreach materials and analyses.
Click here for more information on this CIP project's budget.
| 100% | 08/13/2025 |
Expand to see more
Planning and design only. Design completed August 2025.
Click here for more information on this CIP project's budget.
| 50% | 09/30/2026 |
Expand to see more
Phase 1 improvements completed September/October 2025. Phase 2 (pedestrian improvements) will be continued in 2026.
Click here for more information on this CIP project's budget.
| 35% | 11/30/2027 |
Expand to see more
Finished first round of outreach and developed alternatives for Phase 1 corridors (A St, B St, and Tennyson). Developed alternatives recommended to be analyzed further and presented them to a November CIAC meeting. Started development of Phase 1 second round of outreach materials and analyses. Developed and released Request for Proposals (RFP) for Phase 2 corridors (Hesperian, Mission, and Jackson).
Click here for more information on this CIP project's budget.
| 35% | 12/31/2027 |
Expand to see more
Completed pilot project changes in Q2 2025. Currently evaluating changes.
Click here for more information on this CIP project's budget.
| 35% | 03/31/2027 |
Expand to see more
Prepared an improvement plan based on feedback from public meeting and Council Infrastructure and Airport Committee
Click here for more information on this CIP project's budget.
| 85% | 03/31/2026 |
Expand to see more
Finished last round of internal and external stakeholder outreach. Developed draft plan. Draft plan being reviewed.
Click here for more information on this CIP project's budget.
| 75% | 12/31/2027 |
Expand to see more
Construction completed for fiber, networking, and signal timing for Winton Avenue. Started monitoring phase.
Click here for more information on this CIP project's budget.
| 50% | 09/25/2025 |
Expand to see more
Ongoing implementation of the Neighborhood Traffic Calming Program and responding to resident requests.
Click here for more information on this CIP project's budget.