Livable Neighborhoods > Traffic Calming
Projects
| % Complete | Target Due Date |
|---|
| 0% | January 2027 |
Expand to see more
Construction has not yet started. Estimated 100% Set June 2026. Estimated Bid Advertisement July 2026. Estimated Contract Award August 2026. Estimated Begin Construction September 2026.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 0% | June 2028 |
Expand to see more
Project not yet started.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 5% | June 30, 2028 |
Expand to see more
The grant agreement was executed, and the project officially begun in FY26 (11/17/2025).
This project is mainly supported by a grant from Caltrans' Sustainable Transportation Planning Grant Program, and is currently partially funded by Fund 460 - Transportation Improvement Fund in the amount of $4,500 which does include transfers from the General Fund and Measure C.
Click here for more information on this CIP project's budget.
| 65% | June 30, 2026 |
Expand to see more
Project is at 65% Level as of January 2026. Milestones are: C3, RoW Impacts, 95% Level PS&E.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 65% | June 30, 2026 |
Expand to see more
Project is at 65% Level as of January 2026. Milestones are: C3, Right of Way Impacts, 95% Level PS&E.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 55% | December 31, 2026 |
Expand to see more
Community Engagement - Conducted two outreach events to general public and families of Faith Ringgold Elementary School for input on concept design. Applied for and received grant from Alameda County Transportation Commission for additional funding for design and construction. RFP for PS&E is in review.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 40% | March 2027 |
Expand to see more
Completed first round of outreach and presented recommended Downtown alternatives in an October CIAC meeting to move forward with further analyses and outreach. Started development of round two outreach materials and analyses.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 100% | August 2025 |
Expand to see more
Planning and design only. Design completed August 2025.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 50% | September 2026 |
Expand to see more
Phase 1 improvements completed September/October 2025. Phase 2 (pedestrian improvements) will be continued in 2026.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 35% | November 2027 |
Expand to see more
Finished first round of outreach and developed alternatives for Phase 1 corridors (A St, B St, and Tennyson). Developed alternatives recommended to be analyzed further and presented them to a November CIAC meeting. Started development of Phase 1 second round of outreach materials and analyses. Developed and released Request for Proposals (RFP) for Phase 2 corridors (Hesperian, Mission, and Jackson).
Originally, this project was partially funded by Fund 460 - Transportation System Corridor which does include transfers from the General Fund and Measure C. In order to minimize the impact on General Fund, staff received City Council approval to remove the entire General Fund contribution of $264,000 for the required matching portion of the project and replace with an appropriation from Fund 213, Measure BB (Pedestrian& Bicycle).
Click here for more information on this CIP project's budget.
| 35% | December 2027 |
Expand to see more
Completed pilot project changes in Q2 2025. Currently evaluating changes.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 35% | March 31, 2027 |
Expand to see more
Prepared an improvement plan based on feedback from public meeting and Council Infrastructure and Airport Committee
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 85% | March 2026 |
Expand to see more
Finished last round of internal and external stakeholder outreach. Developed draft plan. Draft plan being reviewed.
Originally, this project was partially funded by Fund 460 - Transportation System Corridor which does include transfers from the General Fund and Measure C. In order to minimize the impact on General Fund, staff received City Council approval to remove the entire General Fund contribution of $264,000 for the required matching portion of the project and replace with an appropriation from Fund 213, Measure BB (Pedestrian& Bicycle).
Click here for more information on this CIP project's budget.
| 75% | December 2027 |
Expand to see more
Construction completed for fiber, networking, and signal timing for Winton Avenue. Started monitoring phase.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 50% | Ongoing |
Expand to see more
Ongoing implementation of the Neighborhood Traffic Calming Program and responding to resident requests.
This project is funded by Fund 460 - Transportation Improvement Fund in the amount of $150,000 for FY26. Fund 460 includes transfers from the General Fund and Measure C.
Click here for more information on this CIP project's budget.