Projects in this category involve beautification, safety, neighborhood amenities, and improvements related to sidewalk and wheelchair infrastructure.

Projects

% Complete Target Due Date
Status Indicators: Complete On Track Ongoing Not Started Pending Delivery On Hold Delayed Abandoned
Community Based Transportation Plan
30%

December 31, 2026

Expand to see more
Project Number: 06940

Activities:

Community Engagement - Conducted outreach to general public and specific communities of interest for input on transportation needs in Hayward's Equity Priority Communities. Developing web map-based survey and general survey for residents to record transportation concerns.Hosted first Steering Committee meeting.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Downtown Specific Plan Implementation (Foothill Blvd., A St., B St., and C St.)
80%

June 30, 2026

Expand to see more
Project Number: 05237

Activities:

Mission Blvd on-street parking pilot program has been installed, helping the City to study the feasibility of a road diet on Mission Blvd. Data collection and outreach are underway to assist with evaluating the pilot project. Remaining Measure B funds will be expended by June 30, 2026.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Safe Routes for Seniors - Tennyson
20%

December 2026

Expand to see more
Project Number: 05323

Activities:

City has provided comments on 100% PS&E and the consultant is revising. Construction expected summer 2026

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Safe Routes to School Implementation Project
20%

October 31, 2026

Expand to see more
Project Number: 06941

Activities:

City has reviewed 60% design submittal drawings and is continuing to develop project PS&E. Project is on schedule for Summer 2026 construction.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.