Sewer System Projects
Projects
| % Complete | Target Due Date |
|---|
| 20% | 2032 |
Expand to see more
Administration building and laboratory is under construction, with anticipated completion in 2027. Phase 2 Improvements design is complete but bidding and construction are on hold pending execution of federal WIFIA loan.
This project has no General Fund or Measure C impact.
| 10% | October 2027 |
Expand to see more
Project bidding completed and is currently in the award phase
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 0% | TBD |
Expand to see more
Not yet started. Engineering staff is working with Utilities Operations and Maintenance staff to review maintenance data and identify utilities to be included in the project. Design is anticipated to start in winter 2026.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 0% | TBD |
Expand to see more
Not yet started. Engineering staff is working with Utilities Operations and Maintenance staff to review maintenance data and identify utilities to be included in the project. Design is anticipated to start in winter 2026.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 20% | TBD |
Expand to see more
Inspection completed for 39-inch Valley View line
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 55% | February 2027 |
Expand to see more
Completed flow monitoring. 24 flow meters were installed at various locations throughout the City for 2 months. Reviewed and processed water/sewer billing data to help calibrate the sewer model. Selected design and capacity criteria.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 80% | Fall 2026 |
Expand to see more
The project is approximately 80% through the schedule. Preliminary studies are complete, and 30% design documents are currently in progress. The project team has also participated in two community engagement events.
This project has no General Fund or Measure C impact.
Click here for more information on this CIP project's budget.
| 90% | August 31, 2026 |
Expand to see more
A draft version of the Recycled Water System Plan document is currently in progress. The final document will include potential projects the City can elect to implement to increase recycled water use involving the expansion of the existing recycled water treatment facilities, and the storage and distribution infrastructure.
This project has no General Fund or Measure C impact.
| 90% | October 2026 |
Expand to see more
All electrical installation items in the Main Switchboard (MSB) building have been completed, with only punch list items remaining open. Painting, flooring, other finishes, electrical cable routing, and programming are currently in progress at the Site Waste Pump Station.
This project has no General Fund or Measure C Impact.
Click here for more information on this CIP project's budget.
| 40% | October 2027 |
Expand to see more
Ongoing activities include exterior and interior framing, gypsum board installation, MEPF (mechanical, electrical, plumbing, and fire service) installations, and underground electrical works.
This project has no General Fund or Measure C Impact.
Click here for more information on this CIP project's budget.