Projects in this category involve beautification, safety, neighborhood amenities, and improvements related to sidewalk and wheelchair infrastructure.

Projects

% Complete Target Due Date
Status Indicators: Complete On Track Ongoing Not Started Pending Delivery On Hold Delayed Abandoned
Campus Drive Sidewalk Improvement Construction Phase
0%

January 2027

Expand to see more
Project Number: 05350

Activities:

Construction has not yet started. Estimated 100% Set September 2026. Estimated Bid Advertisement to follow. 

 

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Traffic Signal & Intelligent Transportation System Master Plan
0%

June 2028

Expand to see more
Project Number: 05351

Activities:

Project not yet started.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Nighttime Safety Enhancement Plan
5%

March 2028

Expand to see more
Project Number: 05359

Activities:

The Nighttime Safety Enhancement Plan will assess and recommend streetlight conditions and illuminance level to improve the nighttime travel safety and reduce any collisions happen in the dark conditions. The project just have began and the City is working with the consultant to collect and assess the existing streetlight conditions and preparing a listening session with Public Works staff to discuss streetlight maintenance, installations, and operations. 

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Campus Drive Sidewalk Improvements -  Phase I 2nd St to Oakes Dr
95%

September 30, 2026

Expand to see more
Project Number: 05344

Activities:

Project progressed from 65% to approximately 95% PS&E (project specifications and estimate). Outstanding items C-3, Right of Way, and public outreach have been successfully completed. Staff anticipates 100% set ready by September 30, 2026 with advertisement and construction of the project to follow.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Campus Drive Sidewalk Improvements -  Phase II Oakes Dr to Highland Blvd
95%

September 30, 2026

Expand to see more
Project Number: 05345

Activities:

Project progressed from 65% to approximately 95% PS&E (project specifications and estimate). Outstanding items C-3, Right of Way, and public outreach have been successfully completed. Staff anticipates 100% set ready by September 30, 2026 with advertisement and construction of the project to follow.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

D Street Traffic Calming & Implementation
60%

June 30, 2027

Expand to see more
Project Number: 05225

Activities:

Request for Proposal (RFP) for PS&E was published and awarded to Bennett Engineering. Project design has kicked off and is expected to be completed towards the end of 2026

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Evaluate Alternatives to Downtown Loop
65%

March 2027

Expand to see more
Project Number: 06945

Activities:

Completed 2nd round of outreach and presented alternatives to Council on June 2nd.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Hayward Blvd. Safety Improvement Feasibility Study
100%

August 2025

Expand to see more
Project Number: 05217

Activities:

Planning and design only. Design completed August 2025.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Hayward Boulevard Safety Improvements
10%

September 2027

Expand to see more
Project Number: 05310

Activities:

Phase 1 improvements completed September/October 2025. Phase 2 (pedestrian improvements) are under design. The City is currently developing topographic survey, which is the first step in developing project Plans, Specifications, and Estimates.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

High Injury Network Safety Plan
50%

November 2027

Expand to see more
Project Number: 06942

Activities:

Completed round 2 outreach and selected preferred alternatives for A Street, B Street, Tennyson Road (Phase 1). Kicked off and collected data and information for Hesperian Boulevard, Mission Boulevard, and Jackson Street (Phase 2).

General Fund/Measure C Impact:

Originally, this project was partially funded by Fund 460 - Transportation System Corridor which does include transfers from the General Fund and Measure C. In order to minimize the impact on General Fund, staff received City Council approval to remove the entire General Fund contribution of $264,000 for the required matching portion of the project and replace with an appropriation from Fund 213, Measure BB (Pedestrian& Bicycle). 

Click here for more information on this CIP project's budget.

Orchard Avenue Traffic Calming
25%

July 2028

Expand to see more
Project Number: 05312

Activities:

Quick build project has been completed. Planning for permanent improvements not started.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Santa Clara Street Traffic Calming Study and Implementation
40%

March 2027

Expand to see more
Project Number: 05313

Activities:

Santa Clara St Safety Improvements Plan was prepared to increase travel safety and slow overall speed. The improvements plan has been presented through the survey and feedback has been collected from the residents and stakeholders. The Plan has been finalized and ready for for construction in August-September 2026.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact.

Click here for more information on this CIP project's budget.

Speed Management Plan
100%

Complete

Expand to see more
Project Number: 06943

Activities:

Completed. Plan approved by City Council.

General Fund/Measure C Impact:

Originally, this project was partially funded by Fund 460 - Transportation System Corridor which does include transfers from the General Fund and Measure C. In order to minimize the impact on General Fund, staff received City Council approval to remove the entire General Fund contribution of $264,000 for the required matching portion of the project and replace with an appropriation from Fund 213, Measure BB (Pedestrian& Bicycle). 

Click here for more information on this CIP project's budget.

Tennyson Rd and Winton Ave Adaptive Signal Coordination Project
90%

December 2027

Expand to see more
Project Number: 05342

Activities:

Infrastructure and signal timing portion of project completed. Currently in monitoring phase.

General Fund/Measure C Impact:

This project has no General Fund or Measure C impact. 

Click here for more information on this CIP project's budget.

Traffic Calming Implementation Program
90%

Ongoing

Expand to see more
Project Number: 05734

Activities:

Ongoing implementation of the Neighborhood Traffic Calming Program and responding to resident requests.

General Fund/Measure C Impact:

This project is funded by Fund 460 - Transportation Improvement Fund in the amount of $150,000 for FY26. Fund 460 includes transfers from the General Fund and Measure C.

Click here for more information on this CIP project's budget.